Question: A project you are working on has a critical path of 36 weeks and a variance of 7 weeks. In order to make important decisions

A project you are working on has a critical path
A project you are working on has a critical path of 36 weeks and a variance of 7 weeks. In order to make important decisions regarding this project, you are calculating the probability of finishing this project within31-38 weeks. What is the probability? a. 45.82 b. 65.45 c. 74.55 d. 94.77 e. None of the above