Question: A project's activity and relationship data is provided in the table. Draw an activity diagram using sequence steps. table [ [ Activity , Successor,IPAs

A project's activity and relationship data is provided in the table. Draw an activity diagram using sequence steps.
\table[[Activity,Successor,IPAs],[1,2,3,-],[2,4,5,1],[3,5,6,7,1],[4,8,2],[5,9,2,3],[6,9,3],[7,10,3],[8,10,4],[9,10,5,6],[10,Finish,7,8,9