Question: A project's base case or most likely NPV is $44,000, and assume its probability of occurrence is 50%. Assume the best-case scenario NPV is 65%
A project's base case or most likely NPV is $44,000, and assume its probability of occurrence is 50%. Assume the best-case scenario NPV is 65% higher than the base case and assume the worst scenario NPV is 35% lower than the base case. Both the best-case scenario and the worst-case scenario have a 25% probability of occurrence. Find the project's coefficient of variation. Enter your answer rounded to two decimal places.
Step by Step Solution
3.46 Rating (153 Votes )
There are 3 Steps involved in it
Coefficient of Variation CV is defined as the ratio of Standard Deviation SD to Expectation E To ... View full answer
Get step-by-step solutions from verified subject matter experts