Question: A project's completion time is uncertain and follows a normal distribution. The project has an expected completion time of 36 weeks, and with a project
A project's completion time is uncertain and follows a normal distribution. The project has an expected completion time of 36 weeks, and with a project variance 7 weeks. The project manager wishes to determine the probability of finishing the project before the given deadline: 26 weeks from today. What is the corresponding z-value in determining the probability? Numbers only. keep 3-decimal if not exact, either round up or down is ok