Question: A project's critical path is ABDE. The project activity information (in weeks) are as follows. Assume the project finish time follows a normal distribution A

A project's critical path is ABDE. The project
A project's critical path is ABDE. The project activity information (in weeks) are as follows. Assume the project finish time follows a normal distribution A B D Activity Expected FT Variance 7 1 5 5 4 9 10 2 9 10 N If the project deadline is set to be 29 weeks, then what is the z-value to determine the probability that the project will be finished before the given deadline? Numbers only. Keep 3-decimal if not exact, either round up or down is ok