Question: A project's critical path is ABDE. The project activity information (in weeks) are as follows. Assume the project finish time follows a normal distribution. If
A project's critical path is ABDE. The project activity information (in weeks) are as follows. Assume the project finish time follows a normal distribution. If the project deadline is set to be 27 weeks, then what is the z-value to determine the probability that the project will be finished before the given deadline? Numbers only. Keep 3tdecimal if not exact, either round up or down is ok
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
