Question: A project's critical path is ABDE. The project activity information (in weeks) are as follows. Assume the project finish time follows a normal distribution. A

A project's critical path is ABDE. The project

A project's critical path is ABDE. The project activity information (in weeks) are as follows. Assume the project finish time follows a normal distribution. A B D E F Activity Expected FT Variance 7 10 5 4 1 4 5 8 2 8 7 2. If the project deadline is set to be 27 weeks, then what is the z-value to determine the probability that the project will be finished before the given deadline? Numbers only. Keep 3-decimal if not exact, either round up or down is ok

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!