Question: A project's duration can be reduced by: * 1 point D) Completing the backward pass first. C) Adding shorter routes around the critical path. A)
A project's duration can be reduced by: *
1 point
D) Completing the backward pass first.
C) Adding shorter routes around the critical path.
A) Shortening the duration of critical path tasks.
B) Adding tasks to the critical path.