Question: A project's duration can be reduced by: Adding shorter routes around the critical path. Shortening the duration of critical path tasks. Adding tasks to the
A project's duration can be reduced by:
| Adding shorter routes around the critical path. | ||
| Shortening the duration of critical path tasks. | ||
| Adding tasks to the critical path. | ||
| Completing the backward pass first. |
2. Between projects A and B, project A will be considered a superior financial undertaking if it has:
| A lower average rate of return than project B. | ||
| A shorter payback period than project B. | ||
| A longer payback period than project B. | ||
| A lower net present value than project B. |
3. Concurrent activities are:
| Activities that can be performed at the same time. | ||
| Activities that use labor from the same group of workers. | ||
| Activities that must be done one after the other. | ||
| Activities that use resources from the same resource pool. |
4. In general, the better candidates for shortening are:
| Early tasks opposed to later tasks. | ||
| Later tasks opposed to early tasks. | ||
| Merge tasks opposed to burst tasks. | ||
| Burst tasks opposed to merge tasks. |