Question: A project's estimated cash flows are summarized below: Year Cash Flow 0 ? 1 $500 2 $400 3 $600 4 $300 The project has a
A project's estimated cash flows are summarized below:
Year Cash Flow
0 −?
1 $500
2 $400
3 $600
4 $300
The project has a payback of 2.6 years. What is the project's net present value (NPV) if the cost of capital of the project is 10%? (Hint: You need to find the cash flow at Year 0 before you calculate NPV.)
Step by Step Solution
3.46 Rating (153 Votes )
There are 3 Steps involved in it
To calculate the net present value NPV of the project we need to first find the cash flo... View full answer