Question: A project's performance has steadily decreased to the point the Project Manager needs to take drastic action Which of the following actions would the Project

A project's performance has steadily decreased to the point the Project Manager needs to take drastic action Which of the following actions would the Project Manager NOT undertake? Consult with the Project Sponsor to obtain additional funds or resources Make the issues known to the project team and seek their additional efforts Begin using cost contingency reserves Decide to cancel the project