Question 17 (1 point) A project's performance has steadily decreased to the point the Project Manager needs to take drastic action. Which of the following actions would the Project Manager NOT undertake? Make the issues known to the project team and seek their additional efforts Decide to cancel the project Begin using cost contingency reserves Consult with the Project Sponsor to obtain additional funds or resources