Question: A purchasing agent is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start
A purchasing agent is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in working days, but the hardware is on backorder and will not arrive for another working days. Fortunately, the purchasing agent has days of slack; however, he shares this slack with the hardware installer. He will have to let the contractor know that the hardware will be ready days later than expected and that the slack for the installer has been reduced by days. The purchasing agent and the installer share days of
a free slack.
b shared slack.
c total slack.
d critical slack.
e functional slack
Which of the following responses best characterizes how to respond to a risk that has considerable upside, or opportunity?
a Mitigate risk
b Avoid risk
c Transfer risk
d Escalate risk
e Retain risk
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock