Question: Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in
Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contractor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share X days of float after delivery. Ox-5 x=9 Ox-10 x-4 x-6