Question: A Quality Analyst wants to construct a control chart for determining whether errors in bank transactions are under control. She looked at samples of 1000
A Quality Analyst wants to construct a control chart for determining whether errors in bank transactions are under control. She looked at samples of 1000 transactions each week, for four weeks in a row. A transaction was considered defective, if the analyst detected any error in the transaction.
| Week | Total Defectives |
| 1 | 30 |
| 2 | 14 |
| 3 | 25 |
| 4 | 44 |
What are the upper and lower control limits for this control chart, using 3 sigma control limits?
| .0436 and .0123 | ||
| .3084 and .2516 | ||
| None of the choices given | ||
| .3226 and .2374 | ||
| .0387 and .0177 |