Question: A Quality Analyst wants to construct a control chart for determining whether five machines, all producing the same product, are under control with regard to

A Quality Analyst wants to construct a control

A Quality Analyst wants to construct a control chart for determining whether five machines, all producing the same product, are under control with regard to a particular quality variable. Accordingly, four units of putputs from each machine are collected:

Machine Measurement 1 Measurement 2 Measurement 3 Measurement 4
M1 78 74 82 75
M2 82 82 83 85
M3 83 80 76 74
M4 76 83 86 79
M5 76 84 81 77

Does this process appear to be out of control? If yes, identify a machine using the factors of three sigma control limits.

a. Process is in Control

b. M1

c. M5

d. M4

e. M2

f. M3

A Quality Analyst wants to construct a control chart for determining whether five machines, all producing the same product, are under control with regard to a particular quality variable. Accordingly, four units of putputs from each machine are collected Machine Measurement 1 Measurement 2 Measurement 3 Measurement 4 M1 78 74 82 75 M2 82 82 83 85 M3 83 80 176 74 M4 76 83 86 79 M5 76 84 81 77 Does this process appear to be out of control? If yes, identify a machine using the factors of three sigma control limits. O a Process is in Control Ob M1 OcM5 Od M4 Oe. M2 Of M3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!