Question: A release has been planned with 5 sprints. The team, for the sake of convenience, has decided to keep the sprint duration open. Depending on
A release has been planned with 5 sprints. The team, for the sake of convenience, has decided to keep the sprint duration open. Depending on how much they commit and achieve, they decide to wrap up the sprint at an appropriate time. Which of the following is CORRECT in this given context ? Select one: O a. This is the best case for a self-organized team O b. This will not work for certain technologies O c. Estimating the velocity would be difficult in such a scenario d. This helps the team to perform at their convenience
Step by Step Solution
There are 3 Steps involved in it
In this scenario the team has decided to keep the sprint duration openended which means the length of each sprint is flexible and can vary based on how much work they commit to and achieve Lets analyz... View full answer