Question: A resource - leveled schedule would have all but one of the following characteristics _ _ _ _ _ _ . a . the project

A resource-leveled schedule would have all but one of the following characteristics ______.a. the project duration could be longer than normalb. slack time is used to begin some activities later than their early start timec. the critical path may be changed
d. a more balanced use of labor resources would be exhibited