Question: A resource loading form can be generated once you have developed: Question 1 8 Select one: a . The work breakdown structure and the project
A resource loading form can be generated once you have developed:
Question Select one:
a
The work breakdown structure and the project budget.
b
The activity network and productivity profile.
c
The project budget and the productivity profile.
d
The activity network and the work breakdown structure.