Question: A resource loading form can be generated once you have developed: Select one: A . The activity network and productivity profile. B . The activity

A resource loading form can be generated once you have developed:
Select one:
A. The activity network and productivity profile.
B. The activity network and the work breakdown structure.
C. The work breakdown structure and the project budget.
D. The project budget and the prodict
 A resource loading form can be generated once you have developed: