Question: A risk response strategy that generally reduces the probability or impact of the event without altering the project's objectives is called: Transter Acceptance Avoidance Mitigation

A risk response strategy that generally reduces the probability or impact of the event without altering the project's objectives is called:
Transter
Acceptance
Avoidance
Mitigation