Question: A sample project consists of the 5 Activities below. Use the chart with the Activities and Durations below to answer questions. Max Crash Duration is
A sample project consists of the 5 Activities below. Use the chart with the Activities and Durations below to answer questions. Max Crash Duration is equal to the shortest possible crashed duration for that activity.
| Activity | Duration (Days) | Predecessors | Max Crash Duration (Days) | Crash Cost/Day |
| A | 5 | - | 3 | $100 |
| B | 3 | - | 1 | $200 |
| C | 4 | A, B | 4 | $0 |
| D | 5 | C | 3 | $300 |
| E | 3 | C | 2 | $400 |
- Draw the AON diagram.
- List all possible paths for the project.
- What is the Critical Path?
- What is the projects expected (best case) duration?
- You have been instructed to reduce the project to 10 days. Crash the project accordingly, based on the information listed. Identify which task(s) you would need to crash in order to reduce to 10 days at the least possible cost?
- You have been instructed to reduce the project to 10 days. Crash the project accordingly, based on the information listed. Identify which task(s) you would need to crash in order to reduce to 10 days at the least possible cost?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock