Question: A schedule / control Gantt chart shows the _ _ _ _ _ _ _ on the vertical axis, and _ _ _ _ _

A schedule/control Gantt chart shows the _______ on the vertical axis, and _______ on the horizontal axis.
Multiple Choice
staffing levels / hours worked
staffing levels / total costs
activities / time and progress
jobs in progress / total costs