Question: A Scrum team has started work on a sprint, with a plan to complete stories U 1 and U 2 , estimated at 3 points
A Scrum team has started work on a sprint, with a plan to complete stories U and U estimated at points each, and story U estimated at points. At the end of the sprint, stories and is complete but is not yet complete, with the unit testing remaining. What is the velocity of the team?
can't be determined