Question: Question 6 A Scrum team has started work on a sprint, with a plan to complete stories U 1 and U 2 , estimated at

Question 6
A Scrum team has started work on a sprint, with a plan to complete stories U1 and U2, estimated at 3 points each, and story U3, estimated at points. At the end of the sprint, stories U1 and U2 is complete but U 3 is not yet complete, with the unit testing remaining. What is the velocity of the team?
11
6
8.5
can't be determined