Question: A semi - automated assembly machine, assembles and welds automotive components for a single shift of 7 . 5 hours, 5 days a week; planned

A semi-automated assembly machine, assembles and welds automotive components for a single shift of 7.5 hours, 5 days a week; planned throughput =150 units/hour; actual output =2875 units/week. The following losses are encountered during
1. Incorrect assembly causes the machine to stop and needs re-set on average 5 times/hr. where 1 unit and 2 minutes are lost. (This leads to performance loss due to minor stoppage and also quality loss)
2. Worn out electrodes are to be replaced once per week, it takes 1 hour when 30 units are scrapped >(availability and quality losses)
3. Burst out cooling hose causes a machine breakdown once in a month and
4. Misaligned fixture causes a loss of 220 units/ week m>(quality loss)5. For different size parts, fixtures to be removed and replaced and electrode position to be adjusted 3 times/week which takes 2.25 hours where 24 units are scrapped each time =>(availability and quality losses)
6. Actuating cylinder sometimes sticks for 30 minutes/d causing production
, oue cyce tme =>(pertormance loss) machine at the
start and end of the day takes 5 minutes each time =>(minor stoppages thereby performance loss)
8. Limit switches corrode once in every 6 weeks stopping the machine and replacement takes 6 hours =>(availability loss).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!