Question: A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Draw
A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Draw the project network. Determine the Earliest Start, Earliest Finish, Latest Start, Latest Finish, and Slack for each activity. Can they complete the project in the class days remaining until the end of the semester?
tableActivity,Time,Immediate PredecessorAFind client,BWrite prospectus,ACtableObtain approval from client andprofessorBDComplete programming,CEDo industry background research,FWrite final paper,D EGWrite oral report,D E