Question: A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both
A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. The project activity schedule and network with the activity times is depicted below. What is the critical path?
Activity
Time
Immediate Predecessor
A
Find client
B
Write prospectus
A
C
Obtain approval from client and professor
B
D
Complete programming
C
E
Do industry background research
F
Write final paper
D E
G
Write oral report
D E
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
