Question: A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both

A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. Draw the project network. What is the minimum time required to finish the project? State the critical path.

Activity

Time (week)

Immediate Predecessor

A.

Find client

4

---

B.

Write prospectus

2

A

C.

Obtain approval from client and professor

3

B

D.

Complete programming

12

C

E.

Do industry background research

10

---

F.

Write final paper

6

D, E

G.

Write oral report

5

D, E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!