Question: A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both
A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. Draw the project network. What is the minimum time required to finish the project? State the critical path.
|
| Activity | Time (week) | Immediate Predecessor |
| A. | Find client | 4 | --- |
| B. | Write prospectus | 2 | A |
| C. | Obtain approval from client and professor | 3 | B |
| D. | Complete programming | 12 | C |
| E. | Do industry background research | 10 | --- |
| F. | Write final paper | 6 | D, E |
| G. | Write oral report | 5 | D, E |