Question: A sequential production line has various tasks assigned to six different stations. The total activity time required to perform the tasks at each station is

A sequential production line has various tasks assigned to six different stations. The total activity time required to perform the tasks at each station is . Use this information to answer the following three questions. BE SURE TO CLEARLY LABEL YOUR ANSWER TO EACH PART. Please show your work.

Station: Total Activity Time
Station 1: 4 minutes
Station 2: 2 minutes
Station 3: 6 minutes
Station 4: 2 minutes
Station 5: 10 minutes
Station 6: 6 minutes

A. What is the station bottleneck. Explain.

B. This production line has capacity to produce how many units per hour? (In the long run, not counting the time that would be required for the first unit to pass through an empty system at startup.) SHOW YOUR WORK.

C. What is the efficiency of the line? SHOW YOUR WORK.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!