Question: A simple CPM network has five activities, A , B , C , D , and E . A is an immediate predecessor of C

A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E.
a. There are two paths in this network.
b. There are four paths in this network.
c. There are five paths in this network.
d. There are 25 paths through this network.
e. None of thes statements is true.
b (Project management techniques: PERT and CPM, moderate){AACSB: Analytic Skills}