Question: A simple CPM network has five activities, A , B , C , D , and E . A is an immediate predecessor of C
A simple CPM network has five activities, A B C D and E A is an immediate predecessor of C and of D B is also an immediate predecessor of C and of D C and D are both immediate predecessors of
a There are two paths in this network.
b There are four paths in this network.
c There are five paths in this network.
d There are paths through this network.
e None of thes statements is true.
b Project management techniques: PERT and CPM moderateAACSB: Analytic Skills