Question: Q1: A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B

Q1: A simple CPM network has five activities, A,
Q1: A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Draw the network path for this project. Q2: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4,B=3,C=8. What is the duration of the critical path. Q3: Draw the critical path for the network activities shown below. What is the duration of the critical path. Q4: The network below represents a project being analyzed by the critical path method. Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H =2,I=10, and J=6. a. What is the duration of path A-B-E-H-J? c. What is the critical path of this network? d. What is the length of the critical path? Q5. Which mission statement of STC. Zain or Mobily you liked the most? Why

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!