Question: A simple CRM network has five activities, A , BCD , and E . A is an immediate predecessor of B and of C .

A simple CRM network has five activities, A, BCD, and E. A is an immediate predecessor of B and of C. B is an immediate predecessor of D and of E. C is an immediate predecessor of E. Which of the following statements is TRUE There are six paths in this network. There are four paths in this network . There are five paths in this network. There are two paths in this network . There are three paths in this network