Question: A simple project network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate

A simple project network has three activities, A,

A simple project network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=3, B=7, C=19. Calculate the EF of activity C