Question: Question 14 (1 point) A simple project network has three activities, A, B, and C. A is an immediate predecessor of B and of C.

Question 14 (1 point) A simple project network
Question 14 (1 point) A simple project network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=9, B=14, C=17. Calculate the EF of activity C. Your