Question: A simple sequential project ( each task must be completed before the next one can begin ) has the time estimates ( in days )

A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below:
\table[[Task,\table[[Best],[Case]],\table[[Most],[Likely]],\table[[Worst],[Case]],\table[[Expected],[Duration]],\table[[Standard],[Deviation]],\table[[Standard],[Deviation],[Squared]]],[A,2,3,4,,,],[B,1,1.5,2,,,],[C,.5,1,1.5,,,],[D,1.5,2,2.5,,,],[E,.5,1,1.5,,,],[F,.4,.5,.6,,,]]
What is the expected total time for the project?
A.7.33 days
B.9.00 days
C.10 days
D.12.67 days