Question: A simple sequential project ( each task must be completed before the next one can begin ) has the time estimates ( in days )

A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below:
\table[[Task,\table[[Best],[Case]],\table[[Most],[Likely]],\table[[Worst],[Case]],\table[[Expected],[Duration]],\table[[Standard],[Deviation]],\table[[Standard],[Deviation],[Squared]]],[A,2,3,4,,,],[B,1,1.5,2,,,],[C,.5,1,1.5,,,],[D,1.5,2,2.5,,,],[E,.5,1,1.5,,,],[F,.4,.5,.6,,,]]
What is the likelihood the project will be completed in 10 days?
A. Between 88 and 88 percent
B. Between 89 and 92 percent
C. Between 93 and 98 percent
D. Between 99 and 100 percent
 A simple sequential project (each task must be completed before the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!