Question: A small project is composed of 9 activities whose time estimates are listed in the table below. Activities are identified by their beginning (i) and

A small project is composed of 9 activities whose time estimates are listed in the table below. Activities are identified by their beginning (i) and ending (j) node numbers. (show your work for each part).

a) Draw the project network and find critical activities and slack times and project duration.

b) What is the maximum number of activities that can be delayed for the project to be on-time? Explain why.

c) Calculate the total usable slack time without delaying the project duration.

Activity

Estimated Duration in Days

i-j

Optimistic

Most Likely

Pessimistic

1-4

17

20

23

1-5

7

10

13

2-3

8

9

16

2-4

16

19

22

3-7

11

14

17

3-8

2

3

16

4-7

2

5

8

4-8

1

4

7

5-6

12

15

18

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!