Question: A small renovation project is to be completed by a general contractor in 6 months for a total cost of $250,000. The projected monthly total
A small renovation project is to be completed by a general contractor in 6 months for a total cost of $250,000. The projected monthly total cost (value) of work scheduled for the project is as shown in Table 2. Table-2: Projected Monthly Total Cost Month 1 2 3 4 5 6 Total cost $20,000 $30,000 $60,000 $75,000 $50,000 $15,000 The breakdown of the cost is as follows: Labor = 30% Equipment = 10% Material = 40% GC/Overhead 10% (GC = General Conditions) Profit - 10% 1) Contractor's Income: a. Payment invoice to owner is submitted monthly on the last day of the month b. Owner's payment is issued 15 days after receiving invoice. c. Retainage is 10% applied to each invoiced payment for the entire project duration. Retainage is paid back in full two months after project completion. 2) Contractor's Expense: a. Labor, equipment and GC/Overhead costs incurred in a given month are expensed at the end of the same month. b. Material costs incurred in a given month are expensed at the end of the following month. 3) A $10,000 residual cash funds (from completing another project will be available to the contractor mid of month four (4) to use towards financing his current project. A small renovation project is to be completed by a general contractor in 6 months for a total cost of $250,000. The projected monthly total cost (value) of work scheduled for the project is as shown in Table 2. Table-2: Projected Monthly Total Cost Month 1 2 3 4 5 6 Total cost $20,000 $30,000 $60,000 $75,000 $50,000 $15,000 The breakdown of the cost is as follows: Labor = 30% Equipment = 10% Material = 40% GC/Overhead 10% (GC = General Conditions) Profit - 10% 1) Contractor's Income: a. Payment invoice to owner is submitted monthly on the last day of the month b. Owner's payment is issued 15 days after receiving invoice. c. Retainage is 10% applied to each invoiced payment for the entire project duration. Retainage is paid back in full two months after project completion. 2) Contractor's Expense: a. Labor, equipment and GC/Overhead costs incurred in a given month are expensed at the end of the same month. b. Material costs incurred in a given month are expensed at the end of the following month. 3) A $10,000 residual cash funds (from completing another project will be available to the contractor mid of month four (4) to use towards financing his current project
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
