Question: A small sample of your project's PERT calculations is shown here. What is the total duration of the project? Activity Optimistic Pessimistic Likely Expected Value

A small sample of your project's PERT calculations is shown here. What is the total duration of the project?

Activity

Optimistic

Pessimistic

Likely Expected Value

1

10

14

12

2

20

30

23

3

3

3

3

a.

33

b.

37

c.

38

d.

47