Question: A small sample of your project's PERT calculations is shown here. What is the total duration of the project? Activity Optimistic Pessimistic Likely Expected Value
A small sample of your project's PERT calculations is shown here. What is the total duration of the project?
Activity | Optimistic | Pessimistic | Likely Expected Value |
1 | 10 | 14 | 12 |
2 | 20 | 30 | 23 |
3 | 3 | 3 | 3 |
a.
33
b.
37
c.
38
d.
47