Question: A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. ACTIVITY IMMEDIATE
A small software development project at Krishna Dhir's firm has five major activities.
The times are estimated and provided in the table below. ACTIVITY IMMEDIATE PREDECESSOR a m b A B C A D B E C Part 2 a) Find the expected completion time for this project. The expected completion time for this project is enter your response here (enter your response as a whole number).