Question: A small software development project has the following major activities. The estimates times are provided below: Activity Immediate Predecessor a m b A - -

A small software development project has the following major activities. The estimates times are
provided below:
Activity Immediate Predecessor a m b
A --258
B A 369
C A 4710
D B 2514
E D 333
F C 6810
G E, F 111
H C 61014
I G, H 345
4. What is the expected completion time for this project?
Answer:
5. What variance would be used in finding probabilities of finishing the project by a certain time?

Step by Step Solution