Question: A small software development project has the following major activities. The estimates times are provided below: Activity Immediate Predecessor a m b A - -
A small software development project has the following major activities. The estimates times are
provided below:
Activity Immediate Predecessor a m b
A
B A
C A
D B
E D
F C
G E F
H C
I G H
What is the expected completion time for this project?
Answer:
What variance would be used in finding probabilities of finishing the project by a certain time?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!