Question: Case 1 ( questions 4 - 5 ) ( SHOW WORK ) A small software development project has the following major activities. The estimates times

Case 1(questions 4-5)(SHOW WORK)
A small software development project has the following major activities. The estimates times are provided below:
\table[[Activity,Immediate Predecessor,a,m,b],[A,--,2,5,8],[B,A,3,6,9],[C,A,4,7,10],[D,B,2,5,14],[E,D,3,3,3],[F,C,6,8,10],[G,E, F,1,1,1],[H,C,6,10,14],[I,G, H,3,4,5]]
What is the expected completion time for this project?
Answer:
5. What variance would be used in finding probabilities of finishing the project by a certain time?
Answer: