Question: A software development project has 9 activities. The activities' durations in weeks and predecessors are as follows: Activity Predecessors Duration A - 6 B A
A software development project has 9 activities. The activities' durations in weeks and predecessors are as follows:
| Activity | Predecessors | Duration |
| A | - | 6 |
| B | A | 4 |
| C | A | 5 |
| D | B | 5 |
| E | B,C | 5 |
| F | E | 2 |
| G | C,D | 2 |
| H | F,G | 5 |
| I | E | 2 |
What is the project duration? ________
The critical path is:
a.A-C-G-H
b.A-B-E-F-H
c.A-C-E-I
d.A-C-E-F-H
e.A-B-D-G-H
What is the free float of activity B?______