Question: For an imaginary software development project the top level Work Breakdown Structure ( WBS ) looks like this: Activity Description Preceding Activity Optimistic Realistic Pessimistic

For an imaginary software development project the top level Work Breakdown Structure (WBS) looks like this:
Activity Description
Preceding Activity
Optimistic Realistic Pessimistic
A Define Requirements None 21018
B Assign Team A 258
C Design Software B 102534
D Code Software B 122034
E Test Software D 305064
F Develop Patent Request C, E 91116
G Build Deployment Package D 303540
H Deploy to Client E, F, G 71517
All duration estimates are in days, and the network proceeds from Activity A to Activity H.
Assume a 5 day work week.
Draw a simple activity-on-node (AoN) network diagram representing the project.
How many paths are possible?
Show, or identify the activities for the Critical Path of this project? How many days?
Which activities demonstrate Slack time?
What is the shortest possible time, in weeks, it will take to complete this project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!