Question: A software development project is behind schedule. The project manager is considering adding more developers to speed up progress. What should be the primary concern

A software development project is behind schedule. The project manager is considering adding more developers to speed up progress. What should be the primary concern before making this decision? The cost of hiring additional resources The rist of increasing communication complexity and inefficiencies The need for additional software tools The avalitability of office space