Question: A software project consists of ten activities whose precedence relationships and time estimates are shown below: Activity: A B C D E F G H
A software project consists of ten activities whose precedence relationships and time estimates are shown below:
Activity: A B C D E F G H I J
Predecessor: - - - - B E C A, F E D, G
Duration: 6 10 11 9 5 8 2 8 7 4
a) find the critical path of the project?
B) What is the corresponding project completion time?