Question: A software project manager must have some work done by an outside contractor. This work has a great deal of risk associated with it, and
A software project manager must have some work done by an outside contractor. This work has a great deal of risk associated with it, and it has become very difficult to find a contractor willing to take on the job.
Which type of contract would offer the greatest incentive to the contractor? Support your answer with appropriate justifications.