Question: A solar panel part assembly line with 20 tasks is to be balanced. The longest task is 3.20 minutes, and the total time for all
A solar panel part assembly line with 20 tasks is to be balanced. The longest task is 3.20 minutes, and the total time for all tasks is 28 minutes. The line will operate for 480 minutes per day. What daily maximum output is theoretically possible for the assembly line?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts