Question: Question 19 (1 point) A solar panel part assembly line with 20 tasks is to be balanced. The longest task is 4.90 minutes, and the

Question 19 (1 point) A solar panel part assembly

Question 19 (1 point) A solar panel part assembly line with 20 tasks is to be balanced. The longest task is 4.90 minutes, and the total time for all tasks is 34 minutes. The line will operate for 480 minutes per day. What daily maximum output is theoretically possible for the assembly line? (please answer to two decimal places, e.g., 10.01) Your Answer: Your